|
|
|
<<<Previous Page |
Index Page>>>
|
|
Half
Yearly Review December 2004
|
Bell Ingram Design
Building Projects – Holyrood or a Bedroom
Extension – Don't Be Hasty at the Idea Stage!
|
|
|
"independent"
Quantity Surveyor or Building Surveyor will
have to be judged as against working solely
with the contractor who is eventually selected
for the project.
|
 |
As
soon as initial sketches are available, approximate
costs can be arrived at and an initial cost budget
can be set. Without this, much time and effort can
be wasted in the "exciting" part of the design process.
For example, we have found that many clients "ignore"
the VAT element of a project in the early stages,
whereas the budget should of course include for
all non-recoverable VAT.
From this point onwards, costs can be held in check
by closely monitoring the complete building process
from inception to completion.
The strength and type of contract is a further key
issue from the earliest stages; approaching a contractor
for "an estimate" has unfortunately on many occasions
been a recipe for disaster, unless every absolute
detail of construction has already been established
and agreed. It is therefore wise to seriously consider
the use of a tried and
trusted form of building contract, the advantage
being that this will establish the requirements
of both employer and contractor in the process and
will allow a clearer control of any modifications
which will undoubtedly arise over the course of
the building works.
In the case of Holyrood, it became very clear during
the inquiry that the design brief had not been fully
established before the contractual process got underway.
This brings into play the other key factors of scale,
quality and programme which need to be addressed
by those at the helm in the very early stages.
If there is an unrealistic emphasis on any of
the main factors above, there will undoubtedly be
a negative influence on one or more of the others.
In many commercial projects, for example, an emphasis
on cost/scale/programme can have a detrimental outcome
on quality. Time restrictions placed on the design
team will equally result in the project not being
fully "designed out" leading to on site difficulties
and cost consequences.
To summarise, therefore, it is important in avoiding
unexpected cost problems at the later stages in
the building process, to consider all the key factors
described above.
I will look at the important issues of the selection
of contractors and ensuring quality in
a future article.
Bill McConnell
|
|
Perhaps
the Holyrood Parliament building (the cost spiralling
from the original budget figure of £40M to the current
final estimated account of £421M) has brought to
the public eye the importance of making the correct
decisions at the earliest stages in the procurement
of any building project. Although I have never actually
heard of a budgeted £40,000 extension rising in
cost to £400,000, the same general principles described
below should apply if the owner / employer is not
to be taken by surprise with costs being more than
anticipated.
Most building projects whether domestic or commercial
will start with the basic idea or requirement for
a new building or extension, for any number of reasons.
This early, concept stage is where the first mistakes
can be made (unless of course cost is not a factor:
I do not come across this situation too often!).
In my view, there are generally four main factors
which should come into play:
Cost
Scale of the project
Quality
Programme
and the correct balance of these factors is the
key to a successful project.
If these factors are considered, the recent spate
of TV programmes embellish how these elements can
easily fall apart, mainly in residential repair
and upgrading projects, but the lessons are clear
for all to learn, if financial problems are to be
avoided.
The control of costs is usually given priority and
an early and correct decision as to how best to
control these costs is a crucial feature.
Much will depend on the scale of the project but
a decision is normally made relatively quickly (possibly
without adequate consideration) on whether or not
"professionals" should be employed to assist in
controlling costs.
The appointment of a suitably experienced

Holyrood
|
|
|
This Review is prepared for general information only. Whilst
care is taken in its compilation, neither Bell Ingram Limited
nor its employees or officers accept any liability for the
contents or their application to any individual circumstances.
Readers are strongly advised to contact Bell Ingram to obtain
advice appropriate to their needs.
|
|
<<<Previous Page |
Index Page>>>
|
|
© Copyright Bell Ingram, 2002 - 2008. All Rights Reserved
Designed By Grange Project
Management
|
|